Real options approach: Case study applied to a nursery to produce Eucalyptus forest seedlings in Brazil

Keywords: geometric Brownian motion, investment decision-making, irreversibility, Monte Carlo, net present value, uncertainty, underlying asset

Abstract

Aim of study: We checked if an infrastructure investment project for a nursery to produce Eucalyptus forest seedlings using the real options approach was economically viable, in order to verify the influence of the deferral, expansion and abandonment options on the investment project value, as well as their concatenation.

Area of study: Our study was based on technical-economic coefficients of a nursery infrastructure to be installed in the São Paulo’s state Midwest region, Brazil.

Material and methods: The investment was assessed by addressing the uncertainties inherent in the investment project. We used the dynamic model for real option approach and, to determine the volatility of the project, we applied the Monte Carlo simulation method. As real options for the project, we employed deferral, expansion, and abandonment.

Main results: Using the traditional valuation methodology, we obtained a negative static net present value of USD 50,957. When incorporating the real options of the abandonment, deferral and expansion in the form of managerial flexibility to forest managers, we obtained the expanded net present value of USD 216,498, that is, 524.8% of valuation. The traditional method of investment evaluation undervalues the project in infrastructures to produce Eucalyptus forest seedlings nursery, and the increase in managerial flexibility, through the real options for deferral, expansion and abandonment, promotes value to forest managers and enables the feasibility of the project.

Research highlights: Infrastructure investment project for a nursery to produce Eucalyptus forest seedlings is not economically viable through the traditional economic evaluation techniques. However, by incorporating managerial flexibilities, through real options, the investment project was valued and it became economically viable.

Downloads

Download data is not yet available.

References

Agliardi R, 2007. Options to expand and to contract in combination. Appl Math Lett 20: 790-194. https://doi.org/10.1016/j.aml.2006.08.011

Arasteh A, 2016. Combination of real options and game-theoretic approach in investment analysis. J Ind Eng Int 12: 361-375. https://doi.org/10.1007/s40092-016-0144-z

B3 S.A., 2020. Cotações históricas. Brasil, Bolsa, Balcão. http://www.b3.com.br/pt_br/market-data-e-indices/servicos-dedados/market-data/historico/mercado-a-vista/cotacoes-historicas/. [14 Feb 2020].

Banco Central do Brazil, 2019. Conversão de moedas. https://www.bcb.gov.br/acessoinformacao/legado?url=https:%2F%2Fwww4.bcb.gov.br%2Fpec%2Fconversao%2Fconversao.asp. [11 Nov 2019].

Benaroch M, 2001. Option-based management of technology investment risk. IEEE Trans Eng Manag 48: 428-444. https://doi.org/10.1109/17.969422

Bhatia S, Mullett TL, 2016. The dynamics of deferred decision. Cogni Psychol 86: 112-151. https://doi.org/10.1016/j.cogpsych.2016.02.002

Bistline JE, Comello SD, Sahoo A, 2018. Managerial flexibility in levelized cost measures: A framework for incorporating uncertainty in energy investment decisions. Energy 151: 211-225. https://doi.org/10.1016/j.energy.2018.03.036

Bowe M, Lee DL, 2004. Project evaluation in the presence of multiple embedded real options: evidence from the Taiwan High-Speed Rail Project. J Asian Econ 15: 71-98. https://doi.org/10.1016/j.asieco.2003.12.001

Brach M, 2003. Real options in practice. John Wiley & Sons, Hoboken. 384 pp.

Brandão LE, Dyer JS, 2005. Decision analysis and Real Options: A discrete time approach to Real Option valuation. Ann Oper Res 135: 21-39. https://doi.org/10.1007/s10479-005-6233-9

Brandão LE, Dyer JS, Hahn WJ, 2012. Volatility estimation for stochastic project value models. Eur J Oper Res 220(3): 642-648. https://doi.org/10.1016/j.ejor.2012.01.059

Brandão LE, Fernandes G, Dyer JS, 2018. Valuing multistage investment projects in the pharmaceutical industry. Eur J Oper Res 271: 720-732. https://doi.org/10.1016/j.ejor.2018.05.044

Bravo F, Fabrika M, Ammer C, Barreiro S, Bielak K, Coll L, et al., 2019. Modelling approaches for mixed forests dynamics prognosis. Research gaps and opportunities. Forest Syst 28(1): 2-18. https://doi.org/10.5424/fs/2019281-14342

Brazil. Constituição, 2006. Lei complementar nº 123, de 14 de dezembro de 2006. Lex: Estatuto Nacional da Microempresa e da Empresa de Pequeno Porte. Brasília, DF. http://www.planalto.gov.br/ccivil_03/leis/lcp/lcp123.htm. [14 Feb 2020].

Caporin M, Rossi E, Magistris PS, 2017. Chasing volatility: A persistent multiplicative error model with jumps. J Econ 198(1): 122-145. https://doi.org/10.1016/j.jeconom.2017.01.005

Chen S, Zhang Q, Wang G, Zhu L, Li Y. 2018. Investment strategy for underground gas storage facilities based on real option model considering gas market reform in China. Energy Econ 70: 132-142. https://doi.org/10.1016/j.eneco.2017.12.034

Cheng C, Wang Z, Liu M, Chen Q, Gbatu AP, Ren X, 2017. Defer option valuation and optimal investment timing of solar photovoltaic projects under different electricity market systems and support schemes. Energy 127: 594-610. https://doi.org/10.1016/j.energy.2017.03.157

Chow JYJ, Regan AC, 2011. Network-based real option models. Transp Res Part B 45: 682-695. https://doi.org/10.1016/j.trb.2010.11.005

Copeland TE, Antikarov V, 2005. Real options: meeting the Georgetown challenge. J Appl Corp Finance 17(2): 32-51. https://doi.org/10.1111/j.1745-6622.2005.00030.x

Cox JC, Ross SA, Rubinstein M, 1979. Option pricing: A simplified approach. J Financ Econ 7(3): 229-263. https://doi.org/10.1016/0304-405X(79)90015-1

Cruz Rambaud S, Sánchez Pérez AM, 2016. Assessing the option to abandon an investment project by the binomial options pricing model. Adv Decis Sci 1-12. https://doi.org/10.1155/2016/7605909

Damodaran A, 2002. Investment valuation: tools and techniques for determining the value of any asset, 2nd ed. John Wiley & Son), 1008 pp.

Damodaran A, 2010. The dark side of valuation - valuing young, distressed, and complex businesses, 2nd ed. Upper Saddle River: FT Press/ Pearson Education. 590 pp.

Damodaran A, 2012. Investment philosophies: successful strategies and the investors who made them work, 2nd ed. Hoboken: Wiley. 609 pp.

Dickey D, Fuller W, 1981. Likelihood ratio statistics for autoregressive time series with a unit root. Econometrica 49: 1057-1072. https://doi.org/10.2307/1912517

DiLellio J, 2017. Real Option modeling and valuation: A decision analysis approach using DPL and Excel. 119 pp.

Duku-Kaakyire A, Nanang DM, 2004. Application of real options theory to forestry investment analysis. For Policy Econ 6(6): 539-552. https://doi.org/10.1016/S1389-9341(03)00003-0

Eyvindson K, Saad R, Eriksson LO, 2017. Incorporating stand level risk management options into forest decision support systems. Forest Syst 26(3): 0-10. https://doi.org/10.5424/fs/2017263-10445

Fleten SE, Linnerud K, Molnár P, Nygaard MT, 2016. Green electricity investment timing in practice: Real options or net present value? Energy 116: 498-506. https://doi.org/10.1016/j.energy.2016.09.114

Gerasimou G, Papi M, 2018. Duopolistic competition with choice-overloaded consumers. Eur Econ Rev 101: 330-353. https://doi.org/10.1016/j.euroecorev.2017.10.002

Geske R, Johnson HE, 1984. The American put option valued analytically. J Finance 39: 1511-1524. https://doi.org/10.1111/j.1540-6261.1984.tb04921.x

Gomez-Cunya LA, Fardhosseinl MS, Lee HW, Choi K, 2020. Analyzing investments in flood protection structures: A real options approach. Int J Disaster Risk Reduct 43: 1-10. https://doi.org/10.1016/j.ijdrr.2019.101377

Guedes J, Santos P, 2016. Valuing an offshore oil exploration and production project through real options analysis. Energ Econ 60: 377-386. https://doi.org/10.1016/j.eneco.2016.09.024

Guj P, Chandra A, 2019. Comparing different real option valuation approaches as applied to a copper mine. Resour Policy 61: 180-189. https://doi.org/10.1016/j.resourpol.2019.01.020

Hach D, Chyong CK, Spinler S, 2016. Capacity market design options: A dynamic capacity investment model and a GB case study. Eur J Oper Res 249(2): 691-705. https://doi.org/10.1016/j.ejor.2015.08.034

Hanafizadeh D, Latif, V, 2011. Robust net present value. Math Comput Modell 54(1-2): 233-242. https://doi.org/10.1016/j.mcm.2011.02.005

Heidari MR, Heravi G, Esmaeeli AN, 2020. Integrating life-cycle assessment and life-cycle cost analysis to select sustainable pavement: A probabilistic model using managerial flexibilities. J Clean Prod 254: 120046. https://doi.org/10.1016/j.jclepro.2020.120046

Hubbard RG, 1994. Investment under uncertainty: Keeping one's options open. J Econ Lit 32(4): 1816-1831.

Ioulianou S, Trigeorgis L, Driouchi T, 2017. Multinationality and firm value: The role of real options awareness. J Corp Finance 46: 77-96. https://doi.org/10.1016/j.jcorpfin.2017.06.011

IPEA, 2020. Emerging markets bond index + Br. http://www.ipeadata.gov.br/ExibeSerie.aspx?serid=40940&module=M. [20 Feb 2020].

Jarque CM, Bera AK, 1980. Efficient tests for normality, homoscedasticity and serial independence of regression residuals. Econ Lett 6(3): 255-259. https://doi.org/10.1016/0165-1765(80)90024-5

Kallio M, Kuula M, Oinonen S, 2012. Real options valuation of forest plantation investments in Brazil. Eur J Oper Res 217(2): 428-438. https://doi.org/10.1016/j.ejor.2011.09.040

Kim K, Ha S, Kim H, 2017. Using real options for urban infrastructure adaptation under climate change. J Clean Prod 143: 40-50. https://doi.org/10.1016/j.jclepro.2016.12.152

Knoke T, Gosling E, Paul C, 2020. Use and misuse of the net present value in environmental studies. Ecol Econ 174: 106664. https://doi.org/10.1016/j.ecolecon.2020.106664

Lin L, Li Y, Jing W, 2018. The pricing of European options on two underlying assets with delays. Phys A Stat Mech Appl 495: 143-151. https://doi.org/10.1016/j.physa.2017.12.031

Martins JC, da Silva RBG, Munis, RA, Simões D, 2022. Investments in Pinus elliottii Engelm. plantations: Real options analysis in discrete time. Forests 13(1): 111. https://doi.org/10.3390/f13010111

Masiero M, Pettenella DM, Secco L, 2016. From failure to value: economic valuation for a selected set of products and services from Mediterranean forests. For Syst 25(1): 1-16. https://doi.org/10.5424/fs/2016251-08160

Mathias JD, Bonté B, Cordonnier T, Morogues F, 2015. Using the viability theory to assess the flexibility of forest managers under ecological intensification. Environ Manag 56: 1170-1183. https://doi.org/10.1007/s00267-015-0555-4

Mei B, Clutter ML, 2015. Evaluating timberland investment opportunities in the United States: A real options analysis. For Sci 61(2): 328-335. https://doi.org/10.5849/forsci.13-090

Miller KD, Arikan AT, 2004. Technology search investments: evolutionary, option reasoning, and option pricing approaches. Strateg Manag J 25(5): 473-485. https://doi.org/10.1002/smj.392

Mintah K, Higgins D, Callanan J, Wakefield R, 2018. Staging option application to residential development: real options approach. Int J Hous Mark Anal 11(1): 101-116. https://doi.org/10.1108/IJHMA-02-2017-0022

Miranda O, Brandão LE, Lazo JL, 2017. A dynamic model for valuing flexible mining exploration projects under uncertainty. Resour Policy 52: 393-404. https://doi.org/10.1016/j.resourpol.2017.04.002

Moon Y, Baran M, 2018. Economic analysis of a residential PV system from the timing perspective: A Real Option model. Renew Energ 125: 783-795. https://doi.org/10.1016/j.renene.2018.02.138

Munis RA, Camargo DA, da Silva RBG, Tsunemi MH, Ibrahim SNI, Simões D, 2022a. Price modeling of Eucalyptus wood under different silvicultural management for Real Options approach. Forests 13(3): 478. https://doi.org/10.3390/f13030478

Munis RA, Martins JC, Camargo DA, Simões D, 2022b. Dynamics of Pinus wood prices for different timber assortments: comparison of stochastic processes. Bois For Trop 351: 45-52. https://doi.org/10.19182/bft2022.351.a36392

Odetayo B, Maccormack J, Rosehart WD, Zareipour H, 2018. A real option assessment of flexibilities in the integrated planning of natural gas distribution network and distributed natural gas-fired power generations. Energy 143(15): 257-272. https://doi.org/10.1016/j.energy.2017.10.114

Olsson O, Hillring B, Vinterbäck J, 2011. European wood pellet market integration - A study of the residential sector. Biomass Bioenerg 35(1): 153-160. https://doi.org/10.1016/j.biombioe.2010.08.020

Padhy RK, Sahu SA, 2011. Real option based six sigma project evaluation and selection model. Int J Project Manag 29(8): 1091-1102. https://doi.org/10.1016/j.ijproman.2011.01.011

Palisade C, 2020. Software Risk Analysis and Risk Modeling, vers 7.6.0. Palisade Corporation. https://www.palisade-br.com/

Peña A, Bonet I, Lochmuller C, Chiclana F, Góngora M, 2018. An integrated inverse adaptive neural fuzzy system with Monte-Carlo sampling method for operational risk management. Expert Syst Appl 98: 11-26. https://doi.org/10.1016/j.eswa.2018.01.001

Pizzirani S, Monge JJ, Hall P, Steward GA, Dowling L, Caskey P, McLaren SJ, 2019. Exploring forestry options with Māori landowners: an economic assessment of radiata pine, rimu, and manuka. N Z J For Sci 49(5): 1-32. https://doi.org/10.33494/nzjfs492019x44x

Pringles R, Olsina F, Garcés F, 2015. Real option valuation of power transmission investments by stochastic simulation. Energ Econ 47: 215-226. https://doi.org/10.1016/j.eneco.2014.11.011

Ray A, Kazantzis N, Foo DCY, Kazantzi V, Tan RR, Bandyopadhyay S, 2021. Financial pinch analysis for selection of energy conservation projects with uncertainties. Chem Eng Trans 88: 109-114.

Rocha K, Moreira ARB, Reis EJ, Carvalho L, 2006. The market value of forest concessions in the Brazilian Amazon: A Real Option approach. For Policy Econ 8(2): 149-160. https://doi.org/10.1016/j.forpol.2004.05.008

Rout A, Sahoo SS, Thomas S, 2018. Risk modeling of domestic solar water heater using Monte Carlo simulation for east-coastal region of India. Energy 145: 548-556. https://doi.org/10.1016/j.energy.2018.01.018

Samuelson P, 1965. Proof that properly anticipated prices fluctuate randomly. Ind Manag Rev 6: 41-49.

Savolainen J, 2016. Real options in metal mining project valuation: Review of literature. Resour Policy 50: 49-65. https://doi.org/10.1016/j.resourpol.2016.08.007

Schachter JA, Mancarella P, 2016. A critical review of Real Options thinking for valuing investment flexibility in Smart Grids and low carbon energy systems. Renew Sustain Energy Rev 56: 261-271. https://doi.org/10.1016/j.rser.2015.11.071

Shukla SK, Sushil, Sharma MK, 2019. Managerial paradox toward flexibility: Emergent views using thematic analysis of literature. Glob J Flex Syst Manag 20: 349-370. https://doi.org/10.1007/s40171-019-00220-x

Soda G, Furlotti M, 2017. Bringing tasks back. In: An organizational theory of resource complementarity and partner selection. J Manag 43(2): 348-375. https://doi.org/10.1177/0149206314535435

Syncopation, 2020. DPL Decision Programming Language. Release 9.00.11. Syncopation Software. https://www.syncopation.com/

S&P Dow Jones, 2020. S&P Global Timber & Forestry Index. https://portugues.spindices.com/indices/equity/sp-global-timber-and-forestry-index. [14 Feb 2020].

U.S. Department of the Treasury, 2020. Daily treasury long term rate data. https://www.treasury.gov/resource-center/datachart-center/interest-rates/Pages/TextView.aspx?data=longtermrate [11 Mar 2020].

Whittet R, Cottrell J, Cavers S, Pecurul M, Ennos R, 2016. Supplying trees in an era of environmental uncertainty: Identifying challenges faced by the forest nursery sector in Great Britain. Land Use Policy 58: 415-426. https://doi.org/10.1016/j.landusepol.2016.07.027

Yusuf SA, Abdul-Qadir MI, Lawal JO, 2014. Determinants of risk and uncertainty in oil palm nursery. J Econ Sustain Dev 5(11): 174-186.

Žižlavský O, 2014. Net present value approach: Method for economic assessment of innovation projects. Procedia Soc Behav Sci 156(26): 506-512. https://doi.org/10.1016/j.sbspro.2014.11.230

Published
2022-11-02
How to Cite
Martins, J. C., Camargo, D. A., Munis, R. A., & Simões, D. (2022). Real options approach: Case study applied to a nursery to produce Eucalyptus forest seedlings in Brazil. Forest Systems, 31(3), e020. https://doi.org/10.5424/fs/2022313-18447
Section
Research Articles